French Vessel Resumes Crete-Cyprus Cable Surveys Until March 2027
A French survey ship left Heraklion on Nov. 10 to resume seabed work for the Greece-Cyprus power cable. Turkey issued its own NAVTEX for Nov. 23 to Dec. 12.

A French survey vessel, the Abeille Marengo, left the port of Heraklion on Crete on Nov. 10 to carry out seabed surveys along the planned Crete-Cyprus electricity cable route, according to To Vima International Edition. Greek and Cypriot authorities had first issued navigational warnings, known as NAVTEX, for the work.
The surveys come after a halt in July 2024 and take place while Turkey has announced a separate research mission of its own in nearby waters. The cable is not being laid yet: the work collects technical data for the design and later installation.
What the surveys cover and for how long
IPTO (Greece’s Independent Power Transmission Operator) and Great Sea Interconnector S.A. (GSI) announced that the first phase of the mission was the calibration of the ship’s survey equipment. The planned seabed investigations followed.
Greek NAVTEX 1411/26, issued by the Heraklion station, covers research operations from Nov. 6, 2026, until March 6, 2027. It lists coordinates east and southeast of Crete towards Cyprus and asks other vessels to stay two nautical miles from the survey area.
A second warning, NAVTEX 345/26, comes from the Cyprus Joint Rescue Coordination Center. It provides for geological survey work by the Abeille Marengo inside the exclusive economic zone (EEZ) of the Republic of Cyprus from Nov. 19, 2026, until March 19, 2027.
Turkey announces its own survey
Turkey has issued NAVTEX 1169/26 for hydrographic surveys by the Turkish Navy research vessel TCG Çeşme from Nov. 23 through Dec. 12. The area lies south of the Turkish coast. Its western edge is south of Kaş, opposite and beyond the territorial waters of Greece’s Kastellorizo island group, and it runs east towards the Antalya region. The notice gives coordinates and asks other ships to keep a wide distance.
To Vima reports that the Turkish notice does not on its face link the mission to the GSI surveys. The two survey areas are geographically distinct, and the notice does not mention the electricity interconnection.
The July 2024 interruption
The GSI surveys were stopped in July 2024 when the Italian research vessel Ievoli Relume met Turkish naval opposition during work off Kasos. That incident began a prolonged period of tension between Athens and Ankara over competing claims on the continental shelf and maritime jurisdiction.
The November resumption followed a new Greek NAVTEX and diplomatic contacts involving France and Turkey. The project is a strategic electricity link between Greece and Cyprus and has European Union support.
Why it matters for readers in Greece
The cable is meant to connect the Greek and Cypriot power systems, and these surveys are a preparatory step. Any further interruption of the work would again make the project a point of friction between Athens and Ankara, as it did in 2024. Readers who follow shipping or sea travel in the southeast Aegean and east of Crete should note that vessels are asked to keep two nautical miles from the Greek survey area.
Dates to watch
- Nov. 19, 2026 to March 19, 2027: the Cypriot warning period for work in Cyprus’ EEZ.
- Nov. 23 to Dec. 12: the Turkish survey by TCG Çeşme.
- Nov. 6, 2026 to March 6, 2027: the Greek NAVTEX period for the route east and southeast of Crete.
Source: To Vima International Edition