Metro Line 4 Moves Evangelismos Work Underground to Spare Rizari Park

Metro Line 4 will build Evangelismos station mostly underground to spare Rizari Park. Kypseli waits for a Dec. 10 expert report on the stalled TBM.

Workers in a dimly lit tunnel construction site with scaffolding and railway tracks, indicating ongoing infrastructure development.
Photo: ds rexy / Pexels

Builders of Athens Metro Line 4 have agreed on a new way to construct Evangelismos station: most of the work will happen underground, and the large surface site once planned for Rizari Park will not go ahead, Proto Thema reported on Nov. 18. The station keeps its planned location near Rizari Street. What changes is how it is built and where its three entrances go.

The redesign does not let crews start right away. It needs new studies, an amended environmental permit and extra construction, and nobody has said yet who covers the added cost or how large it will be.

How the Evangelismos plan changes

Under the original method, crews would have dug a large pit at street level. They will now reach the station mostly from below, working out of the existing site on Vasileos Konstantinou Avenue where the tunnel-boring machine (TBM) came out of the ground. This keeps most of Rizari Park intact, including its most significant trees, and avoids heavy traffic changes on Vasilissis Sofias Avenue, which was another weak point of the first plan.

The three entrances are also being moved:

  • one at the junction of Rizari Street and Vasileos Konstantinou Avenue;
  • one on the side of Evangelismos Hospital;
  • the main entrance in front of the current metro exit that leads toward Rizari Park.

The main entrance is where the only sizeable surface dig remains. A limited excavation pit will be opened there, with construction access from the Hilton side so that the site takes up less of the park.

Who agreed, and what still has to happen

Rizari Park has been the subject of a long legal dispute with shipowner Nikos Pateras. According to Proto Thema, the new solution was shown to him as early as the summer, and Mayor Haris Doukas of Dimos Athinaion (the Municipality of Athens) appears to back it. The paper describes the understanding as a decisive step toward avoiding further legal action over the station.

The design is still being developed. An Environmental Impact Assessment is being prepared, and it will be the basis for the Ministry of Environment and Energy to amend the project’s existing approval of environmental terms. No timetable has been set for that process, so the start date for building with the new method is unknown.

Cost is the largest open question. The contractor’s earlier estimates put the extra cost at around €50 million, while more recent, unconfirmed information puts it at €100 million. Sources at the Ministry of Infrastructure told the paper the final figure depends on finishing the technical studies and on how much additional work is needed.

Kypseli waits for a Dec. 10 report

The second problem on Line 4 is in Kypseli, where the TBM has stood still since May 8 after ground subsidence and damage to buildings along its path. British professor Robert Mair is expected to submit his report on Dec. 10. It will assess the technical evidence and set out the work needed before anyone decides whether the machine can safely restart.

His conclusions are not yet clear. During a recent visit to Kypseli he appeared reassuring that the problems could be handled with technical measures. Repairs will cost extra, Proto Thema reports, although the amount is unknown.

Relations between residents, the municipality and Elliniko Metro, the company building the line, have grown more tense in recent days over the extent of the damage, building safety and the conditions for restarting work.

What this means for Kypseli residents

The Kypseli Residents’ Initiative called for a large turnout at the Athens Municipal Council meeting on Wednesday, Nov. 18. It is asking for:

  • structural adequacy checks for every building in the zone of influence;
  • full repair of the damage;
  • relocation of affected residents to suitable housing, with expenses covered;
  • a guarantee that the TBM will not be restarted under any circumstances.

Deputy Minister of Infrastructure Nikos Tachiaos said in a radio interview on Tuesday that residents could be moved temporarily if repairs inside apartments or safety concerns require it. He said recent work on one apartment building had been approved by that building’s management. He also blamed a local residents’ group for the tension, saying it was trying to take a role in the construction process beyond what it is entitled to.

For commuters, the line’s timetable now depends on two separate steps: the environmental approval for Evangelismos and the measures Mair recommends for Kypseli. Readers can see how the network’s existing routes connect in our guide to Athens metro lines and interchanges.