Athens Mayor Asks Metro Firm to Rehouse Kypseli ‘Red’ Block Residents

Athens Mayor Haris Doukas wants everyone in Kypseli apartment blocks rated red over metro works moved to safe housing at the metro company's cost.

A modern multi-story apartment building under construction with scaffolding and safety netting.
Photo: Magda Ehlers / Pexels

Athens Mayor Haris Doukas on Monday asked the state metro company to move out, immediately and temporarily, everyone living in the Kypseli apartment blocks that inspectors have classed as “red” because of the metro construction works, the financial daily Naftemporiki reported.

Doukas wants residents placed in safe accommodation, with the metro company and the project’s contractor carrying both the responsibility and the bill.

What the mayor’s letter asks for

The request came in a letter sent Monday to the two top officials of Elliniko Metro A.E. (Hellenic Metro, the company that builds the Athens metro): its chairman, Sp. Chrysanthopoulos, and its chief executive, Chr. Fafoutis. Naftemporiki published the letter in full.

In it, the head of Dimos Athinaion (the Municipality of Athens) writes that urgent measures are needed to protect the people living in these buildings. He asks for all occupants of the red-rated blocks to be relocated for now to safe lodgings, and says the cost should fall on Elliniko Metro and on the construction company carrying out the project. He closes by saying he expects the company to act as quickly as possible.

The letter does not say how many buildings or residents are involved, and it gives no deadline.

Which buildings are rated red

The classification comes from inspections by expert assessors of the Techniko Epimelitirio Elladas (the Technical Chamber of Greece, the professional body for engineers). According to the mayor, their checks so far have put apartment blocks in the red category, and he names one as an example: the building at 92-94 Spetson Street in Kypseli.

Doukas says the municipality recently learned more from a letter that Elliniko Metro itself sent to affected Kypseli residents. That letter, he writes, said the assessors had advised immediate measures at the Spetson Street building to improve and restore the way the footings under its facade are bedded in the ground. Footings are the parts of a foundation that spread a building’s weight into the soil.

The mayor reads that recommendation as a warning of immediate danger.

What it means for Kypseli residents

For people living in the red-rated blocks, the letter is a formal demand made on their behalf. It is not an evacuation order. Doukas is asking the metro company to act, and Naftemporiki’s report does not include a reply from Elliniko Metro or from the contractor.

If the company agrees, residents of those buildings would leave their homes for a period while living in accommodation paid for by Elliniko Metro and the contractor. The mayor’s wording covers everyone staying in the buildings, which would take in tenants as well as owners.

The letter also puts on record who the municipality holds responsible. Doukas places both the duty to rehouse people and the expense on the company running the metro project and on the firm building it, and does not assign either to the city.

Residents of other buildings near the works have a point of reference too: the Technical Chamber’s assessors are the ones classifying the blocks, and Elliniko Metro has already written directly to affected households in Kypseli about what those assessors found.

Source: Ναυτεμπορική